HRP Stocking Up on Derringer Cases

We are running the Haas CNC mill 7 days a week at the moment. Machining our cases takes about 5 different operations. Each operation takes about 1 1/2 hours per case half to machine. Multiply 8 engine blocks (that is 16 halfs) times 5 operations, that is 80 total operations, now time the 1 1/2 hours per, that equals 120 hours. If you get 8 full hours of machining time in per day, it takes 15 days to run the 8 complete engine blocks. We will finish them up tomorrow and move on to the next pile of aluminum sitting on the floor, LOL. JV